Bromley Heath viaduct works from 22 July - reminder and details




We’ve already reported on the works to the Bromley Heath viaduct on the Ring Road, which will have major travel implications across our area.

Although the Government was not prepared to stump up any more cash, the West of England Joint Committee did recently agree funding from the Local Enterprise Partnership Economic Development Fund (EDF) to reduce the work from 52 weeks to 33 weeks. So the extra cash is being taken from other regional projects, it's not "new money".

Traffic management will be put in this weekend, Saturday 22 to Sunday 23 July, and the actual maintenance work will start on Monday 24 July.

South Gloucestershire Council have put together some very clear web pages on the project here

One key issue is the best routes to avoid some of the jams. For example, to get to the M32 the Winterbourne route from Yate will be better than going via Coalpit Heath. The same web page shows the changes at Winterbourne traffic lights.